Decentralised Power Supply

Legal support for decentralised power supply

David Engel advises on direct lines, on-site supply, self-supply, customer installations (Kundenanlage) and charging infrastructure, from the choice of supply model through grid connection to the contracts. For industrial companies, project developers and energy service contractors.

Eight years of experience in energy law, in law firms and in the legal department of an industrial company.

Starting points

Typical situations in practice

As of 14 November 2026.

01 · Direct line

Supply from a generation plant nearby

A solar or wind farm nearby supplies the site via its own line. The site's grid connection remains in place for residual electricity and back-up.

  • In law: Direct line under Section 3 no. 27 EnWG, and following the CJEU judgment of 17 September 2026 (C-722/24 and C-756/24) also where the grid connection continues to exist. No network charges or levies are incurred on the line.
  • In practice: The grid connection question: a separate connection for the plant or the site's connection. It needs to be settled before the first contract.

02 · On-site supply

A third party's plant on the company premises

An energy service contractor or project developer builds and operates a PV plant on the premises and supplies the company. The surplus is fed into the grid via the site's connection.

  • In law: On-site supply agreement with use of land and metering concept, feed-in via a third party's connection, lease of the plant as an alternative.
  • In practice: The metering concept, because levies, electricity tax and direct marketing depend on how the volumes are delineated.

03 · Self-supply

Own generation plant with surplus feed-in

The company operates PV, CHP or storage itself and feeds in the surplus.

  • In law: Self-supply, direct marketing from 100 kW, electricity tax and supplier status, and with third-party capital a lease or operations management.
  • In practice: Grid connection agreement, controllability of the plant, deadlines for direct marketing and the core energy market data register (Marktstammdatenregister).

04 · Customer installation (Kundenanlage)

Supplying other companies at the site

Service providers, subsidiaries or tenants draw electricity via the site's lines.

  • In law: Onward supply to third parties. For installations connected by 23 December 2025, grandfathering under Section 118(7) EnWG applies until 31 December 2028. New cases involving the sale of grid electricity to several customers are now possible only to a limited extent.
  • In practice: The cut-off date and the question of whether grid electricity or only self-generated electricity is passed on.
Article: Electricity distribution at industrial sites →

05 · Charging infrastructure

Charging points at the site

Charging points for the fleet, employees and visitors, often with PV and storage, operated by the company or a third party.

  • In law: Grid connection and load management, GEIG, the Charging Station Ordinance (Ladesäulenverordnung), calibration law, operator model and billing.
  • In practice: Who operates the charging point determines the obligations and the billing.
Services

Site check for power supply

Supply model and grid connection question for a specific project as a short opinion with a meeting, at a fixed fee. The result is a recommendation with the next steps towards the network operator and contract partners.

Direct supply contract package

Electricity supply agreement, line and land agreements, residual electricity and direct marketing, tailored to the chosen model.

Obligations and deadlines schedule

Overview of the obligations and deadlines under statute and grid connection conditions, together with the required registrations, updated across the project phases.

AI is used for document review, research and contract analysis. The time saved is passed on in the price. More: Energy and commercial law with AI

Enquiries to mail@engel-legal.de or +49 931 73041732.

Project path

A direct supply example

On the left the typical steps of the project, on the right the legal work in each phase, using the example of supplying a site from a generation plant nearby.

Project · Milestones
ENGEL | LEGALLegal support
01

Structuring

  • Load profile of the site and generation profile of the plant
  • Decision on the connection concept: a separate connection for the plant or the site's connection
  • Letter of intent between operator and offtaker
ENGEL | LEGAL
  • Choice of supply model and roles: operator, supplier, offtaker
  • Grid connection questionWhether the feed-in commitment stays at the plant's location, is transferred to the offtaker's connection, or the plant is split into two separate parts each with its own connection. The connection rules do not allow two grid connections to be coupled. and feed-in commitment
  • Charges: network charges, levies, electricity tax, supplier status
  • EEG: direct marketing, award, allocation of volumes between direct supply and feed-in
  • Term sheet

Obligations and deadlines schedule drawn up

02

Network operator

  • Connection request and grid compatibility assessment
  • Technical connection concept and metering concept
  • Grid connection agreement
ENGEL | LEGAL
  • Connection concept with the network operator: feed-in limitation, zero feed-in, decoupling
  • Legal requirements for the metering and balancing concept
  • Grid connection agreement and connection use
  • If refused: right to connection under the EEG and EnWG

Obligations and deadlines schedule updated: deadlines arising from the feed-in commitment and grid connection agreement

03

Contracts and investment decision

  • Land rights and rights of way secured
  • Electricity supply agreement signed
  • Residual electricity supply adjusted
  • Investment decision
ENGEL | LEGAL
  • Electricity supply agreement: price, volumes, availability, curtailment, term, green electricity attribute
  • Line: construction, ownership, easements, permission to use public roads
  • Residual electricity agreement and the site's existing supply agreement
  • Direct marketing agreement for the surplus
  • Lease or operations management agreement, agreement on the energy management system

Obligations and deadlines schedule updated: deadlines and notification duties

04

Commissioning and operation

  • Commissioning by the network operator
  • Registration in the core energy market data register (Marktstammdatenregister)
  • Ongoing supply
ENGEL | LEGAL
  • Notification and reporting duties: core energy market data register (Marktstammdatenregister), main customs office, network operator
  • Guarantees of origin and environmental claims towards customers
  • Legal questions of billing: delineation of volumes, levies, electricity tax
  • Disruptions, curtailment, claims against contract partners

Obligations and deadlines schedule updated: ongoing notification and reporting duties